Edit the report outline
Go to Finance > Reports > Reporting (Finanzen > Berichte > Berichtswesen) and open any report.
In the business object "Report display" (Berichtsdarstellung), select Edit outlines (Gliederungen bearbeiten).
Initially, you can create the missing standard definitions (1).
These serve as a starting point and can be edited or duplicated.
The account assignment in the standard reports is based on SKR03, so this assignment must be revised. The same applies to cost centres and cost units.
You can export (exportieren) an existing outline via (2) in order to import it into other companies with the CSV import (CSV-Import) (3).
With Add (Hinzufügen), you create an empty outline. With Edit (Bearbeiten), you open a selected outline.
You can also Remove (Entfernen) or Duplicate (Duplizieren) selected outlines (and then edit the copy further).
Change dimension accounts (Dimensionskonten ändern) allows you to replace the cost centre reference in value rows (see below) with a different reference.
You get several cost centre reports, for example per department, if you first define an outline for one cost centre. By duplicating it and swapping the cost centre, you quickly get a set of similar cost centre reports. You can call up all these sub-reports via multiple selection within your main report.
The components of an outline
The header area contains details of the Report type (Berichtsart), Report name (Berichtsbezeichnung) and Report description (Berichtsbeschreibung).
The five report types are: balance sheet, P&L (GuV), cost centre report, cost unit report or other report (for example, BWA).
With Account names (Kontennamen), you can use a language selection for the account names. The alternative names must be stored in the account master.
The Report authorisation (Berichtsberechtigung) controls the access right to the outline.
In the table below, you see the individual report rows.
Edit a row of the report outline
Each report row has a name that can be maintained directly in the table.
The row number (2) determines the order in the sub-report.
When building a report, leave enough space between the row numbers. The row numbers can only be adjusted individually afterwards and cannot be moved in blocks. A gap of 10 rows, or better 20, is a good measure.
The row type (3) defines the content of the row and can be selected from a drop-down.
In the assignment (4), you can see whether values have also been assigned to the row.
Possible row types
Result row (Ergebniszeile)
Totals several rows of the reportP&L value (G&V Wert)
Special row for reports of the balance sheet type. It determines the current P&L value from the balance of the P&L accounts. No additional G/L accounts may be stored in such a row.Profit carried forward/loss carried forward (Gewinnvortrag/Verlustvortrag)
Deficit not covered by equity (Nicht durch Eigenkapital gedeckter Fehlbetrag)
Special row for reports of the balance sheet type.Percentage row (Prozentzeile)
A percentage value is output in a percentage row.Calculation row (Rechenzeile)
The values of two rows of the sub-report can be combined using the four basic arithmetic operations or set in a percentage ratio.Heading (Überschrift)
Text row that outputs the name from the column of the same name.Value row (Wertezeile)
Here, the data from the posting journal is determined on the basis of account, cost centre or cost unit.