Procurement settings: order control, bill of materials and picking

Procurement settings in Scopevisio for order control, bills of materials, picking, inventory and reservations, plus rules of the supply structure.

This article describes the procurement settings for order control, bill of materials, picking, inventory and reservations, as well as the rules for picking and supply structure. Paths, prerequisites, import, goods receipt and warnings are described in the article Procurement settings.

Which settings are there for order control, parts lists and picking?

Order BOM

The order BOM is a technical system that is central to the functionality of procurement. When procurement is activated, Scopevisio generally generates it at the time the order is saved. It contains the following information in particular:

  • Products, quantity, unit, stock price

  • Location

  • Requested date

With the order BOM, you can track the status of quantities, products and items of the order. This way Scopevisio can calculate a delivery date, write a reservation and finally also generate the order proposal.

Always set this setting to Always generate as soon as you want to use procurement.

Requested date

In contrast to the delivery date of an order, the requested date is not aimed at your customer, but primarily at you as an organization. It is the date on which your customers regularly request the fulfillment of their orders. When you use parts lists for the procurement of individual components, it serves to agree on a defined, clear date, also in communication with your suppliers.

Use the default setting of today, tomorrow etc. to pre-set the majority of orders to the correct date with minimal data maintenance. You can still adjust the date at order level. Scopevisio always includes the requested date in all communication so that the requested date is fulfilled as well as possible.

After updating parts lists

Parts lists for a defined product can be subject to general, dynamic or specific changes. This setting regulates how such a change takes effect.

Starting from a defined product with a complete parts list, it may be necessary to adjust an individual item, because a product is not available, has a successor or because another one fits better. It may also be necessary to extend the parts list, because additional elements were required to complete it that were not previously known.

There are two extremes for handling such changes:

  • The automatic system updates all orders accordingly.

  • The setting update prices only makes it possible to display products in different compositions on the same parts list.

Allow manual editing of order BOMs

The system creates and maintains order BOMs automatically. With this setting, you additionally allow manual interventions in the order BOM, for example to adjust individual items that deviate from the standard.

Important: Activate this setting only if your processes regularly require such deviations. Manual changes can limit the traceability of the automatic logic.

When executing order control

This setting regulates the handling of entries for maximum stock levels. The quantities of a product in orders can be above the defined maximum stock level. The setting determines which entry has priority:

  • Ignore maximum limits: You can fully cover your requirements from orders, even if the maximum limit could technically speak against it.

  • Respect maximum limit: Scopevisio reduces the order proposal in the requirement quantity to the maximum limit.

The decisive question is whether the maximum limits set per product are of a technical nature. An example: you can only store a certain amount of milk and butter, after which you run out of storage space and everything spoils. In that case, you should respect the maximum limits. If you do not face such a problem, Ignore maximum limits is recommended in order to fulfill all orders as quickly as possible.

Use future receipts

This setting affects the goods receipt and the corresponding posting of the stock.

The setting No means: With the posting date, Scopevisio posts exactly the stock of the goods receipt, and it is immediately available for all orders. Scopevisio calculates the planned date for the delivery of the order on exactly the delivery date. Under certain circumstances, this can lead to undesirable behavior, because in the second a goods receipt is deemed posted, the goods are not yet available at the storage location for picking the order.

In terms of content, the function corresponds to an inbound warehouse lead time. An example: You complete the goods receipt on day 1 and set the future receipts to 2 days. You then have 2 days to put the goods away at the storage location. The planned date of the order is pulled along accordingly.

This system helps you to structure your processes internally. Instead of individual information on when the goods reached the storage location, you regulate the general structure via standard lead times and can possibly bring these down to 1 day over time.

When picking is carried out

Here you control which events happen when picking is carried out. You can print a list, send a list by email or both.

  • When you use paper, it is best to print the list centrally.

  • When you use the warehouse app 2Go, set 2Go: do nothing else.

This system is related to the fact that Scopevisio already debits the stock from the warehouse when picking is carried out.

Booking date of picking

In most cases, the booking date is today. If you want to start a picking now that is only to be executed later, set here that the picking you initiated today is executed in x days.

Allow partial picking with quantities

Scopevisio calculates all planning data, delivery options etc. for the entire order, but shows when individual items can be delivered in full. You pick these with the command Teilkommissionierung.

If you want to deliver in smaller units and pick not just an entire item but a partial quantity of the item, set this setting to Yes.

Note: Picking the quantities individually is a much higher effort (internal costs) than delivering the entire order and carrying out a partial picking as an exception.

Check picking

This command transfers the picking to the 2Go warehouse app. Above all, this changes the posting behavior: from direct debiting with the picking command to the time at which the withdrawal is documented in the app.

Default type for inventories

This setting defines which inventory type Scopevisio suggests by default when you create a new inventory. The key date inventory records the stock on a defined key date, typically at the year-end closing. Select the type that corresponds to your regular inventory process.

Hide calculated quantities (inventory)

The setting Berechnete Mengen ausblenden defines the suggested value for new inventories. If the option is on in an inventory, Scopevisio hides the calculated quantity and the difference during counting, and the counted quantities start at 0. Your employees then record the actual stock without being influenced by the book value. This corresponds to the principle of blind counting (blind inventory). If the option is off, the counted quantity is pre-filled with the calculated stock.

In the inventory itself, the option is also called Berechnete Mengen ausblenden (column Bestand ausblenden in the overview). You can only change it there as long as the inventory has not yet started.

Match incoming invoice automatically (ReBU)

Incoming invoices can be matched automatically with the associated goods receipt. If quantity and price match, Scopevisio assigns the invoice directly to the goods receipt, without manual intervention.

This setting considerably reduces the manual effort in the incoming invoice process. However, it requires that order data, goods receipts and invoice data are maintained consistently.

Create reservations for product types

Scopevisio distinguishes 4 different product types: goods, material, right and service. With this setting, Scopevisio creates reservations for the respective product type for products that have a base unit. As a consequence, an order proposal is also generated. Scopevisio only takes a product from an order into account if it has a base unit and its product type is marked here as reservable. Scopevisio does not take blocked products into account.

Take this into account in connection with the master data of products: Which products should be reserved, for which products should an order proposal be generated and for which should it not?

Which rules are there for picking and supply structure?

Apply requirement request rule

The requirement request logic is inactive by default. You activate it with this setting (Yes/No). Only then does the system fall back on the configured rules during picking.

Via the 3-dot menu (Weitere Aktionen) in the procurement settings, two rule configurations are available. Together they control the automatic stock transfer during picking.

Picking rules

Access: Procurement settings → Weitere Aktionen → Regeln zur Kommissionierung bearbeiten

Picking rules define whether and under which conditions a stock transfer between locations is triggered automatically when picking an order or a requirement request. They are the link between the configured supply structure and the actual warehouse movement.

Without a configured picking rule, no stock transfer takes place. The stock is withdrawn directly at the target location, provided it is sufficiently available there.

Requirement request rules

Access: Procurement settings → Weitere Aktionen → Bedarfsanforderungsregeln bearbeiten

Requirement request rules define which source location supplies which group of requirement requests, and thus from where stock is transferred during picking.

Basic principle: Requirement requests are divided into groups. Each group has exactly one assigned source location and exactly one target location. The assignment is 1:1: A group is always supplied by exactly one source and supplies exactly one target.

Several groups can be used to map differentiated supply structures:

  • Group North: Source location Hamburg warehouse, target location Kiel branch

  • Group South: Source location Munich warehouse, target location Augsburg branch

Supply logic: If an order or a requirement request at the target location triggers a picking, the system checks whether a rule with a matching source location is stored for the associated requirement request group. If so, Scopevisio automatically triggers a stock transfer from the source location to the target location. The stock is transferred automatically with the picking and increased at the target location. This means the regular logic of inventory, orders, manual postings etc. applies.

Note: Exactly one source and one target are permitted per requirement request group. If no rule is configured or no matching group applies, no automatic stock transfer takes place.