Create, send and approve purchase orders

Here is how you create purchase orders in the Scopevisio Client, send them and have them approved, plus the four ways a purchase order comes about.

With purchase orders in the Scopevisio Client, you create and document a contract, in particular a purchase contract, with your supplier. You open them in the ribbon under Procurement → Orders. This article shows how a purchase order is created and how you create, send and have it approved. Order confirmation, import and goods receipt have their own articles (see below).

This article applies to users with procurement activated and the right to the Purchase order form. By default, the Purchaser profile has this right, see Roles and rights for procurement.

Process overview of procurement from order proposals via orders and goods receipts to invoices and payments

Process overview: The sales process from orders to payments and below it the procurement process from order proposals via orders, goods receipts and invoices to payments

Where do I see all my purchase orders in the Scopevisio Client?

In the Scopevisio Client, click Orders in the ribbon. The overview shows all purchase orders with their status and all related information. Like every overview in Scopevisio, it is organised as a worklist. You can filter it using arguments and save the filters as a personalised worklist:

  • Use quick filters for targeted overviews

  • Create individual worklists and save them under a specific name

What can I do in the purchase order overview?

From the purchase order overview, you have the following options:

  1. Add a new purchase order: Click Add.

  2. Edit an existing purchase order: Double-click a row to open the purchase order.

  3. Duplicate a purchase order: Create a copy of an existing purchase order.

  4. Transfer a purchase order to a delivery: Start the goods receipt directly from the overview.

  5. Import a purchase order via CSV: Use the multibutton for mass imports.

In which ways is a purchase order created in Scopevisio?

A purchase order can be created in four ways. All routes lead to the same result: a legally documented purchase contract with the supplier, which serves as the basis for goods receipt and invoice verification.

Create a purchase order from an order proposal

Replenishment planning creates order proposals, but no purchase orders. The purchase order is only created when the purchaser accepts the proposal with Transfer to order (or In Bestellung überführen und versenden).

The basis of the order proposals are open orders, requirement requests and the stock. You store the reorder point as well as the minimum and maximum stock per product and location or storage bin. If the stock falls below the reorder point, the next replenishment planning creates an order proposal up to the maximum stock, not immediately when the goods are withdrawn. Replenishment planning runs when events occur and additionally once a day.

Replenishment planning preferably selects the default supplier, otherwise another supplier of the product that is valid on the order date. If the product has no valid supplier, Scopevisio creates the order proposal without a supplier. Then enter a supplier before saving or ordering.

This route is the standard case for stock-managed products and recurring consumables. It is most efficient when you maintain assortment and suppliers in the master data. More on this in the article Order proposals.

Create a purchase order from an order enquiry

The order enquiry is used to obtain quotations from one or more suppliers before a binding purchase order is triggered. After receiving and comparing the quotations, you transfer the order enquiry to a purchase order.

This route is suitable if price or supplier is not yet determined, for example for larger procurement projects, new products or if you want to compare several suppliers. More on this in the article Order enquiry.

Create a purchase order directly from a customer order

With the procurement license activated and the corresponding right, the Transfer to order button appears in the customer order. Scopevisio creates a purchase order directly from it. Project number, all items and the supplier proposed from the product suppliers master data are taken over. The reservation of the customer order is considered fulfilled for the items taken over. No additional order proposal is created.

This route is suitable if supplier and terms are already known and no stock check is required, typically for project-related individual procurements or the direct commissioning of a service provider. More on this in the article Direct order from customer order.

Create a purchase order manually

You can create a purchase order at any time directly from the purchase order overview, without a predecessor and without an automatic proposal. You enter supplier, products, quantities and prices manually.

This route is suitable for one-off procurements, new suppliers or as an entry into the process if there is not yet a complete master data basis. It is also possible without order control. The efficiency gain from automatic assignment in the background is retained.

Steps: Create a purchase order manually in the Scopevisio Client

  1. In the purchase order overview, click Add.

  2. Select the supplier from your contacts.

  3. Using Add, select the products and quantities you want to order.

  4. Adjust prices and units if necessary. This is possible in an individual purchase order.

The quantity is documented in the Delivery quantity field. If the master data record for product suppliers, units and prices is maintained, Scopevisio takes this information over into the purchase order.

How to search for and add products, insert text lines, set the delivery date and service period and which fields a purchase order has is described in the article Edit a purchase order: items, dates and fields.

Steps: Send a purchase order in the Scopevisio Client

You can send the purchase order to the supplier directly from the form. You have the following shipping options:

  • Send by letter

  • Send by e-mail (including PDF attachment)

Sending by e-mail is the default everywhere. As the recipient address, Scopevisio uses the business e-mail address of the contact.

Additional functions are available when sending:

  • Text modules for the document

  • Text modules for the e-mail

  • Add further documents from Teamwork

  • Change of the sender for the individual dispatch

Set the sender address for sending purchase orders

You define the e-mail address from which Scopevisio sends purchase orders with the setting E-Mail Absender (Bestellung). It only applies to purchase orders. You find the setting in two places, which edit the same setting:

  • In the Scopevisio Client under Settings → Funktionsbereiche → Procurement → Allgemein

  • In the ribbon Organization → Stammdaten → Procurement → Settings

The following selection is available:

  • System: Scopevisio uses the sender from the e-mail settings of the system. This is the default.

  • Aktueller Benutzer: Scopevisio uses the current user as the sender.

  • Supplier advisor: Scopevisio uses the address of the supplier advisor of the purchase order. It is preset from the setting of the same name.

  • Manuell: You store a fixed address and a name.

In the send dialog, the sender is preset with this setting. You can change it for the individual dispatch. Exactly one valid e-mail address is permitted.

Purchase order status after sending

After sending by e-mail or letter, the purchase order status changes automatically. This makes it traceable for everyone that the supplier knows the purchase order. You do not have to clarify whether an individual purchaser has sent the purchase order. This is clearly visible to everyone in the system and speeds up the process.

Approval process for purchase orders

Scopevisio can submit purchase orders for approval via the Allgemeiner Freigabeprozess. The approval process exists for purchase orders and for quotations to customers, not for order enquiries. You must activate it as the function Allgemeiner Freigabeprozess and set it up using rules. A threshold is one possible rule, but not the only one.

While the approval of a purchase order is running, the following applies:

  • You cannot send the purchase order

  • You cannot confirm the purchase order

  • You cannot transfer the purchase order to a goods receipt

  • Editing and saving remain possible

  • Printouts bear the note "not approved"

Scopevisio sends an e-mail to the approving person only if the notification template is active.

What happens after the purchase order has been sent?

  • Supplier's order confirmation: You apply the confirmation to the purchase order, manually or read automatically. This is only possible as long as no goods receipt has been posted. More in the article Process the supplier's order confirmation for a purchase order.

  • Import purchase orders: You create purchase orders from files (CSV, EDI, XML) via the import. More in the article Import purchase orders.

  • Goods receipt: From the purchase order, you transfer it into a delivery and post it. More in the article Goods receipts.

Typical process of a purchase order in Scopevisio

  1. Entry: You enter product, quantity, price and unit and transmit this to the supplier.

  2. Supplier response: The supplier responds with planned delivery date, product confirmation, quantity confirmation and price confirmation.

  3. Order acceptance: After order acceptance, the confirmed delivery date and confirmation are available, and the status changes.

  4. Delivery: On delivery, the actual delivery date, documents (for example the delivery note) and the posting of the stock are added.

If posting a goods receipt for a purchase order does not work

If the setting Delivery postings require full order matching is active in the procurement settings, Scopevisio can only post a goods receipt or delivery note if the entire quantity of each product item is allocated to purchase order items.

  • Cause: The goods receipt has no purchase order reference, or the delivered quantity is above the open order quantity. Saving is possible in both cases, posting is not

  • Solution: Allocate the quantities of the product items to the purchase order items via Order comparison. Partial deliveries are allowed; the purchase order itself does not have to be fully delivered for this. If the setting is switched off, Scopevisio posts a surplus quantity without a purchase order reference. How the setting works is described in the article Procurement settings.

If the confirmation from the supplier can no longer be applied to the purchase order, a goods receipt has usually already been posted. The reasons are described in the article Process the supplier's order confirmation for a purchase order, section "Until when can I apply the order confirmation?".

If the problem persists, ask in the chat to be connected with the support team.

Frequently asked questions about purchase orders

Does an order proposal automatically create a purchase order?

No. Scopevisio only creates a purchase order from an order proposal when the purchaser accepts the proposal with Transfer to order (or In Bestellung überführen und versenden).

Does an order proposal need a default supplier?

No. A default supplier is not a prerequisite for an order proposal. If the product has no valid supplier, Scopevisio creates the order proposal without a supplier. Before saving or ordering, you enter a supplier.

Related articles about purchase orders